Archway House, Canary Wharf, London E14
Appointed to complete the extension to Archway House in London. Gorge Fabrications provided detailing, fabrication, intumescent painting and the installation of the structural steel frame.
Refurbishment and extension using structural steelwork package.
Market Sector: Office
Client: Lambeth Council
Contract Value: £1,5 million

Main Contractor: Buxton Building Contractors Limited
Engineer: O’Connor Sutton Cronin & Associates Ltd
Architect: TTSP Architecture & Design

Tunsgate Quarter (Retail Shopping Centre Development)
Tunsgate Quarter offers something new for Guildford. A unique combination of premium fashion shopping and contemporary dining in one destination situated between the historic High Street and medieval castle.
Gorge were appointed to deliver the detailing, manufacturing and installation of the structural steel frame.
Market Sector: Retail
Client: Merseyside Pension Fund / Queensberry Real Estate
Contract Value: £700,000

Main Contractor: ISG PLC
Engineer: Jubb Consulting Engineers Ltd
Architect: Lyons Sleeman Hoare Architects

Erdington Leisure Centre
A brand new sport and leisure facility for Erdington, Birmingham.
Gorge Fabrications were appointed on a JCT contract to provide the detailing, manufacturing and erection of the hot rolled structural steelwork package. The programme also consisted of cold roll purlins fittings, painting steelwork over the swimming pool, placement of pre-cast concrete blanks, metal decking and 2 precast stair cases over 4 flights of stairs.
Market Sector: Leisure Centre
Contract Value: £700,000

Main Contractor: ISG Plc
Engineer: Nolan Associates – Civil & Structural Engineers
Architect: Calderpeel Architects

Ivor House – 682 Lambeth Civic Centre, London
Gorge Fabrications were selected to provide the structural steelwork and related metalwork packages on this landmark urban development in Lambeth. The Civic Centre in Lambeth comprises of five floors of modern office space for Lambeth Council above a Customer Services Centre on the ground floor.
Appointed to provide Detailing, Fabrication and Erection of Structural steel frame on this multi-storey office building. Including column strengthening, and installation of internal stair cases, roof and metal decking to the building.
Market Sector: Office
Client: Muse Developments
Contract Value: £400,000

Main Contractor: Morgan Sindall
Engineer: Curtins Consulting Ltd
Architect: Cartwright Pickard Architects Ltd.

Multi-Storey Car Park Stoke-on-Trent
Gorge were appointed on a JCT Design & Build basis for this 2 Storey Car Park Project. This involved the full Design, Detailing (using of CAD), Fabrication and Erection of the core Structural steelwork package. Including the delivery of the metal stair cases, ramps, metal decking, cladding, concreting floors, fire doors and safety barriers.
The project was delivered within programme and cost.
Market Sector: Multi Storey Car Park
Client: Goodwin International Ltd
Contract Value: £600,000+

Main Contractor: Gorge Fabrications Ltd
Architect: HBL Associates (Consulting & Civil Engineers)

Car Park Mercedez Benz Croydon – 76 Purley Way Croydon
Gorge were recently appointed on a JCT Sub contract basis for this single Storey Car Park Project in Croydon This involved the full Detailing, Fabrication and Erection of the core Structural steelwork package. In addition to which Gorge are contracted to supply and install the Metal Staircase, Ramp, Barriers and the Balustrades providing almost the full solution.
This project completed in February 2018 on-time and to client requirements.
Market Sector: Car Park
Client: Mercedez Benz
Contract Value: £300,000

Main Contractor: ARJ Construction
Engineer: Axiom Structures
Architect: Ayshford Sansome